Half A Billion ALL: The Municipality Of Tirana Receives 11 Additional Contracts, Fusha Takes 301 Million

Half A Billion ALL: The Municipality Of Tirana Receives 11 Additional Contracts,

For infrastructure investments, the Municipality of Tirana has procured billions of ALL, at least in the last two years, contracts which in almost half of the cases have been developed without competition.

But in addition, an amount of 519.8 million ALL has been added to the companies that have been declared winners of the initial contract.

And according to APP data, from 2018 to June 2020, the municipality of the capital has approved 11 additional contracts.

Fusha company through negotiation has won more than half of their total.

Only through two additional contracts, the economic operator in question has received a fund of about 301 million ALL.

It is about the Urban Requalification of Skënderbej Square, the first and second phase.

An initial fund of 105.5 million ALL has been added to the initial contract for the first phase, while for the second phase the value reaches the figures of 195.6 million ALL.

However, the latest addition to a contract turns out to be the one given in June this year with a value of 12.6 million ALL.

Through negotiation, this contract was awarded to the union of economic operators RSM Company and Egland Shpk.

English News municipality of tirana fusha company